Paul Murphy presses ESB on data centres and housing connections

Paul Murphy presses ESB on data centres and housing connections

Paul Murphy questioned energy network representatives about Castle Bagot, housing connections and data centre capacity during Oireachtas proceedings. He also asked whether the Greater Dublin area is constrained for new data centre applications and whether data centres should disclose energy and water use.

Castle Bagot and housing


Murphy challenged officials on reports that the Castle Bagot substation’s capacity had been taken up by a data centre, delaying housing connections. Officials said they were not aware of housing delays caused by the substation and said data centres had transferred from an existing supply point, freeing capacity in the area.

Dublin’s electricity constraints


Murphy asked whether the Greater Dublin area is considered constrained for new data centre applications. Officials said the Large Energy Users Action Plan and a CRU direction identify constraints in Dublin, while allowing for limited opportunities to be considered case by case.

Paul Murphy — still from speech: Paul Murphy presses ESB on data centres and housing connections (29.09.2026)

Energy and water disclosure


Murphy also asked whether data centres should be required to disclose their energy and water consumption. Officials said decisions about responsibility for tracking this information would be a matter for national policy.

Watch the recording to hear the full exchange.

We publish thousands of recordings to make Irish politics transparent and resistant to manipulation. Spotted an error? Report it — together we are building a reliable archive of Irish politics.

Tego samego dnia All speeches from this day →

Transcript
Thanks a lot. I'll start with ESB networks. I want to ask about Castle Bagot, which is reported as a substation, cost 100 million euros or so, and it was reported that housing was delayed in being available for sale and use because the data centre connected first and effectively took up the capacity. Is that accurate? This question has come up just about the general point about data centres and how data centres impacted on our ability to connect houses. If you look at the overall situation in North and West Dublin, and Dublin is the biggest concentration of data centres at transmission level and distribution, so there's two things that come up around network capacity when it comes to data centres. Is there transmission capacity available for the distribution network? And then at distribution level, can we continue to connect houses? And we are continuing to connect houses. In West Dublin and North Dublin, we are seeing continued growth in housing overall, and maybe I'll ask Alan to come back in on this question. We're seeing a big uplift in housing this year. Sorry, I'm asking about Castle Bagot, if I can get an answer to the question. Castle Bagot is impacting on that West Dublin area, and we're continuing to connect houses there at the present and since. Were houses today being connected because of a data centre? Not to my knowledge. Not that I'm aware of. Part of what was connected at our existing supply point was a number of data centres that subsequently transferred into Castle Bagot, which freed up capacity in the area to enable us to continue to connect housing in the area. And in PR6, there is plans for another bulk supply point, which is the interface substation between the transmission and distribution station, and that is planned to be starting in PR6 and completed in PR7. Okay. I think it's important maybe, can I ask, Deputy, just around housing connections in general. There can be various reasons why houses can take longer or shorter, depending on the level of work that can be required, and it's usually done at distribution level, where work is required at a local substation, whether it be designs to be done, but that is different to a transmission-connected data centre at the likes of Castle Bagot or others. Just to check, I read in the Irish Times article, the Castle Bagot 220 substation was intended to relieve pressure on the grid and support housing and industrial growth, but officials noted the, quote, sheer volume and energy density, end quote, of data centres in the area, start quote, completely consumed the capacity of the new reinforcement, end quote. That's not accurate. Well, it's, I think you're referring to a presentation that AirGrid gave to the department, maybe in 2024, if that's the one that you're referring to. It's the Department of Energy here, but yeah. So just maybe to comment on this, and it might help explain it a bit further. When Castle Bagot was being developed initially, there was an intention, now I wasn't directly involved, there was an intention that it would support further development at distribution level, including housing, in that area in West Dublin. What happened subsequently was there was a large volume of large users who came in to connect data centres, but has that delayed housing in West Dublin? That's a different question. We've continued to connect housing in West Dublin and right across the Dublin area during that time. Now, I don't know if there's any comments from colleagues in AirGrid around this, because look, we weren't involved in that meeting. Let me just add a little bit. When we build a transmission station, it's obviously for a number of reasons, so we would have requests from ASP Networks directly as a distribution system operator. That could be for, it's called a bulk supply point, so they'll request a certain import capacity into the distribution system from the transmission system, and that might be for housing, electrification and transport, a number of different reasons, and smaller industrial development and smaller, and other sort of formats of use. We'll take all of those into consideration and we'll plan the system accordingly, so the transmission system will be there for multiple reasons. In addition to that, parties can come along and apply to connect to that, along with the distribution system operator. We continue to respond, as ASP Networks understand what the needs are of their system, we continue to respond with those bulk supply points. Just to confirm, there was no delay in the connection of housing as a consequence of this? Not that I'm aware of, yeah. Just to go back to AirGrid then for my final, you say in your opening statement, additionally, applications cannot proceed in constrained areas. Can you tell me what are constrained areas? I mean, if I understand correctly, in the Greater Dublin area, 80% of our electricity is going to data centres. Is the Greater Dublin area counted as a constrained area, or is it more limited? There's a number of applications that support that. There's the Large Energy Users Action Plan, in terms of the future development of data centres and large energy users overall, the Large Energy Users Action Plan, and also the CRUs direction that came out at the back end of 2025, which we're looking to implement along with ASP Networks. In both of those documents, it talks about the constraints that are applied in the Greater Dublin area, so both documents talk to the fact that Dublin is a constrained area, and that goes back to as far as the 2021 direction. So there'll be no more applications can proceed in the Greater Dublin area? Within that, what it also notes is that within the Large Energy Users Action Plan, we'll continue to work with government under the legend to see if there are limited opportunities for development in the Dublin area, so that's where we are, and we'll respond to them on a case-by-case basis. But they cannot proceed, isn't that good? Deputy, we're out of time. You did say cannot proceed in the opening statement, but you're saying they might proceed sometimes? Deputy, we're moving on, we're moving on. Deputy, Charlie Mytham. Do you think that data centres should be required to disclose energy and water consumption? So in terms of energy consumption, that might be similar to the question that Deputy Gibney posed on the energy efficiency directive. Again, we have no remit with regards to energy efficiency, which might track consumption, if I can put it that way. In terms of water... Sorry, would you like to have the capacity to do it, or be given the capacity to do it? I think that is a policy matter, and it's up to national policy to determine what entity might be best suited to do it. Would you be in favour of that policy? I think the energy efficiency directive is an important component of the European ACHE relating to energy. I think it will support our energy management nationally when it comes in, as to whether we're the right organisation or not, I don't know, and that would be down to the policy holders to determine that.