Brian Stanley: Data centres are putting huge pressure on the grid

Brian Stanley: Data centres are putting huge pressure on the grid

Brian Stanley questions the impact of rising electricity demand from data centres on Ireland's public network, household bills and wider infrastructure. He sets out the government's response, including the Large Energy User Action Plan, PR6 grid investment and new connection conditions to manage demand.

Key points and role of data centres


Brian Stanley explains that data centres provide essential digital infrastructure and support nearly 190,000 ICT jobs, but their rapid proliferation is placing significant pressure on the electricity grid. He highlights studies and reports indicating that almost a quarter of available supply is already used by data centres and that this share could exceed one third.

Infrastructure investment and local impact


The deputy details the PR6 grid investment programme: around 520 capital projects and roughly 18.9 billion pounds earmarked for transmission and distribution upgrades over the next five years. He references recent local delivery, including the opening of the Bracklone 110 KV substation in Leash, and regular engagement with Airgrid and ESB to monitor progress.

Household costs and regulation


Stanley raises concerns that network upgrades are adding costs to household electricity bills, noting network charges have risen 175% between 2020 and 2026. He stresses that while data centres are strategically important, their energy use must be managed so that households and other sectors are not unfairly burdened.

Policy response and conditions for connections


The description summarises the Large Energy User Action Plan published in January and the plan-led approach to connection agreements. Future connection criteria include bringing forward renewable energy - aiming for 80% new renewable supply as a condition - and clearer processing rules to avoid first-come, first-served approvals.

Housing, water and mixed economic growth


Stanley warns that concentrating too much supply in one high-profit sector can distort the economy and hamper housing and water connections. He calls for a measured approach that balances digital infrastructure with jobs, housing and other public services.

We publish thousands of recordings to make Irish politics transparent and resistant to manipulation. Spotted an error? Report it — together we are building a reliable archive of Irish politics.

Tego samego dnia All speeches from this day →

Transcript
Minister, can I ask about the impact of electricity demand on data centres on the public network? What studies are being carried out by your department to determine the impact in terms of the costs on householders and in terms of additional costs to the public in general? It's not a case of getting up and arguing against all data centres, you know there will be data centres but the proliferation in this country is very high and they are having a significant impact on the grid and on costs. Many deputies have raised this matter and understandably today I've answered in detail but to answer yourself just for fair repetition that data centres do provide that essential digital infrastructure for our economy and they do strengthen our position as a strategic knowledge intensive location for digital and the tech sector. I mentioned earlier on we've about just short of 190,000 people working in ICT, so it is very significant, we're not a large heavy industrial country in relation to heavy industry but ICT I would contend is that sector and the digital infrastructure is underpinned in many ways by data centres that provide significant support to all areas of our economy. What we did though deputies, we brought forward the large energy user action plan and published that in January of this year, that sets out the plan led approach to enable Ireland to attract the next generation of investment in strategic energy intensive sectors in the medium to long term. It will ensure that future growth remains aligned with Ireland's green transition, energy affordability and security objectives, as well as other strategic government priorities such as the provision of housing, transport and water. Government remains committed to investing in critical infrastructure to deliver electricity to a growing population and a growing economy, with new housing and expanding businesses so our grid investment programme provides a historic investment in Ireland's electricity grid infrastructure, up to about £18.9 billion, over 520 capital projects to be delivered from the period now over the next five years and they include 29 significant transmission infrastructure projects and 32 distribution substations and I regularly meet every month actually with Airgrid and with ESB on their work programme to monitor that investment. Actually in your own area in Leash in July I was really delighted to open the ESB networks new the Bracklone 110 KV substation in Leash and that was actually the first major substation delivered under this capital programme and that will have a massive positive impact on the area and on energy and electricity capacity in Leash and particularly the Portleisha area. Yes, there is significant work going on on the network and an upgrade and that's badly needed but there's a cost to that and the outlying 190,000 jobs, very few of them jobs are actually linked directly, are actually in data centres, the point I'm making here is that almost a quarter of the available supply is being used by data centres and there's reports saying that it could go over one third and higher, that's huge pressure on the network and that's putting a lot of pressure on Airgrid and on the ESB etc to upgrade the grid and put in significant investment in there and I'm for the investment in it because I'm welcoming in my own area the opening of that substation because it's needed for the increased industry and jobs in the area and increased population and not to mention the housing that's being built. Recent studies show that it is putting an extra cost on householders and you know the data centres are getting cheaper electricity than Jo and Mary public, that's the point, they're getting cheaper electricity but the public are paying for the upgrade, there's an upgrade levy now on everyone's bill and that's the key point I think Minister that you need to take home, we have a huge proliferation of them compared to other EU states and some American states are saying no to them now, some of the American states are saying no, not in our patch but we're accepting everything and I think we just need to have a more measured approach to this. Yeah, look, it's important that we debate it but not every application is accepted and I don't just accept every application that comes in for a connection, connection agreements, applications are made and they can be accepted or refused but we've set out how new applications have to be processed in a plan led way, it's not just first come first served or you apply for a data centre or you apply for whatever and you get it but PR6, the grid investment programme actually outlines how and what we need to do to get ahead of that, of the energy demand projections and it's a big programme, what I would say, I mentioned earlier on in response to another deputy's question in relation to the network charges, network charges are obviously set by the Commission for Regulation Utilities, I don't set them but I know you didn't say that but I just wanted to say in relation to data centres between 2020 and 2026 the network charges have increased by 175%, so that's just to put the facts on the floor of the House in that regard, but it has to be managed appropriately, I agree with you on that and that's what's being done. Margaret Harker. There's a number of things here that if we're going to construct 50,000 homes per year and again there was reports this week that the supply of housing has been hampered by the supply of water, water connections and electricity, there's clearly a pull factor there and the point is that the thing that government have to take into consideration is that there has to be jobs in other sectors as well, there has to be homes built, we know that there's pressure here every day with people talking about it, we're putting pressure on government on it, government are under pressure, they're putting pressure on officials and local authorities to step up to the plate and drive on the programmes there as well, so we have to look at things in and around here, but we do have a habit in this country and I don't want to give you a history lesson to go back to the crash and all that, we have an often habit in this country of putting too many eggs into one basket and it's a high profit industry, we're accepting them, I agree with you, not everyone of them has passed, gets planning permission, but the sheer number that's going in and the supply of water and electricity going into them can throw this economy off to one side and can have a negative effect on other sectors, that's the key point here. Margaret. Just very briefly, I responded earlier on in relation to water usage and Ishaq Eireann estimated about 0.3% of water is actually used at data centres, that's their figures, so just again to put that on the record of the House, but to reiterate it does have to be managed and we're doing that, and that's why myself and Peter Burke brought forward the large energy user action plan, because that sets out how in a plan led way, where there is capacity, and if 80% of the energy is brought forward through new renewable sources, that that is one of the conditions of future connection agreements for data centres, so we haven't seen a large number of data centres connected over the last couple of years, so there isn't a case that, and to be fair to you, you've acknowledged this, that an application is made not even for planning, I'm talking for connection agreements, not every connection agreement is granted either, but we've set down very clearly what the criteria for getting a connection agreement is now, and that's important, and it's important we manage this demand and projected demand well and appropriately.